11 33KV 3 phase 300 kva dry type transformer outage maintenance
1、Switching operations, safety protection, and safety warnings before inspection
a. Disconnect the low-voltage side circuit breaker of the transformer to be maintained, pull down the isolating switch, and hang the corresponding sign on the handle.
b. Disconnect the load switch on the high-voltage side of the transformer, confirm that it is in the disconnected position, then close the grounding knife, and complete the safety insurance of the switch and hang the relevant identification plate.
c. Check electricity, discharge, and hang grounding wires on the high and low voltage sides
2、Equipment inspection, dust removal and cleaning
Temperature controller:
a. If the temperature controller does not display, first check whether the fuse is blown. If it is blown, replace it with a fuse of the same specification.
b. Wipe off the dust on the temperature controller and re-tighten the connecting screws of the temperature controller’s control circuit.Fan: Tighten the screws for the fan power connection and the fixing bolts of the fan. Purge all parts of the fan with clean compressed air or oxygen.
11 33KV 3 phase 300 kva dry type transformer outage maintenance
| Rated capacity | 300 kva |
| Rated voltage | 6KV/10KV/33KV/35KV/40.5KV |
| model | SCB(10)-300/10/0.4KV or SCB(11)-300/10/0.4KV orSCB(12)-300/10/0.4KV orSCB(13)-300/10/0.4KV orSCB(14)-300/10/0.4KV or as per requirement |
| type | Dry type (cast resin) |
| No. of phase | 3 |
| Tapping range | ±2X2.5% |
| Vector Group | Dyn11/Yyn0/as per requirement |
| Winding material | Copper/Aluminum |
| Core material | GO Steel |
| Cooling method | AN/AF |
| standard | GB 1094/IEC 60076 |
| Winding Temperature Rise | F insulation class(100K) H insulation class(125K) |
| No load loss | as per requirement |
| Load loss | as per requirement |
| Short circuit impedance | 6% |
| shell | Cold-Rolled Steel Sheet(IP20/IP23)/Stainless Steel |
11 33KV 3 phase 300 kva dry type transformer outage maintenance

FAQ About QIANLAI’s 300 kVA Dry Type Transformer
What is the MOQ for your 300 kVA dry type transformer?
The minimum order quantity is 1 unit. We welcome both bulk orders and customized small-batch projects to meet your specific needs.
Do you provide OEM/ODM services?
Yes. As a factory-direct supplier, we offer full OEM/ODM services, including custom logos, specifications, and packaging. Our engineering team will work with you to design the perfect solution.
How long is the lead time?
Standard models are in stock with a lead time of 3-7 days. Customized 300 kVA dry type transformers take 15-25 days, depending on the complexity of the requirements.
What after-sales support do you offer?
We provide 2-year warranty, free technical consultation, and on-site installation guidance. Our global service team responds within 24 hours to resolve any issues.